Methods Specific to Data Projects

General methods (predictive, agile, and lean) say almost nothing about what makes a data project unique: data is an unstable material, its condition is only known once you…

Guide≈ 33 min readPartly checkedPartial checkThe main facts were checked by searching the cited sources. The items below still need checking before relying on them.To re-check
  • Statut actuel de maintenance de la documentation TDSP et d'ASUM-DM : non confirmé par une source primaire (formulations prudentes conservées dans la page).
Written with AI assistance; sources are cited at the bottom of the page. An error? Report it via clement13.net.
Reading
In brief
  • General methods (predictive, agile and lean) say almost nothing about what makes a data project unique: data is an unstable material, its condition is only known once you open it, and the “truth” of the result is negotiated with the business.
  • You'll learn how to position and compare CRISP-DM, ASUM-DM, TDSP, the Kimball lifecycle, DataOps, data products / Data Mesh, MLOps/AIOps, DAMA-DMBOK, then the five project families (analytics/machine learning, BI/datamart, migration, governance, quality).
  • You'll learn how to choose: which method for a BI/datamart project, which one for a machine learning project, which one for a quality initiative.
  • Each method is rated /5 according to the file criteria (see RATING); ratings are contextual expert assessments.
  • Methods are combined: the general case is “Kimball for modeling + Scrum/Kanban for steering + DataOps for industrialization”.
On this page
  1. 1. Why a method specific to data
    1. 🟢 Novice — what changes when data is the material
    2. 🟡 Practical — the five families of data projects
    3. 🔴 Expert — the shifted “cone of uncertainty”
  2. 2. CRISP-DM
    1. 🟢 Novice — the model
    2. 🟡 Practical — how to use it today
    3. 🔴 Expert — limits and extensions
  3. 3. ASUM-DM
    1. 🟢 Novice — an IBM extension
    2. 🟡 Practical — when to cite it
    3. 🔴 Expert — critical reading
  4. 4. TDSP (Team Data Science Process)
    1. 🟢 Novice — Microsoft's method
    2. 🟡 Practical — what you can reuse without adopting it
    3. 🔴 Expert — limits
  5. 5. The Kimball Lifecycle
    1. 🟢 Novice — the data warehouse reference
    2. 🟡 Practical — ideas that still matter
    3. 🔴 Expert — Kimball vs. modern practices
  6. 6. DataOps
    1. 🟢 Novice — applying the DevOps mindset to data
    2. 🟡 Practical — two pipelines, two loops
    3. 🔴 Expert — measuring DataOps
  7. 7. Data products and Data Mesh
    1. 🟢 Novice — thinking in “product” terms
    2. 🟡 Practical — what this changes for project management
    3. 🔴 Expert — Data Mesh: when and when not
  8. 8. MLOps and AIOps in brief
    1. 🟢 Novice — two acronyms, two meanings
    2. 🟡 Practical — what changes in project management
    3. 🔴 Expert — specific pitfalls
  9. 9. DAMA-DMBOK
    1. 🟢 Novice — the data management framework
    2. 🟡 Practical — how to use it without getting lost in it
    3. 🔴 Expert — critical use
  10. 10. Data governance managed as a project
    1. 🟢 Novice — what it is, what it is not
    2. 🟡 Practical — start it as a value-driven project
    3. 🔴 Expert — why it fails, how we know
  11. 11. The data migration project
    1. 🟢 Novice — why it is a project in its own right
    2. 🟡 Practical — phases and controls
    3. 🔴 Expert — reconciliation and idempotence
  12. 12. The BI / datamart project
    1. 🟢 Novice — the most common form
    2. 🟡 Practical — a recommended composite method
    3. 🔴 Expert — structuring trade-offs
  13. 13. Data quality projects
    1. 🟢 Novice — fix the cause, not just the symptom
    2. 🟡 Practical — the quality loop
    3. 🔴 Expert — trade-offs
  14. 14. Comparison Table and Ratings
  15. 15. Pitfalls and good practices
  16. 16. AI Contribution
  17. 17. See also

Level: 🟢→🔴

1. Why a method specific to data#

🟢 Novice — what changes when data is the material#

In a traditional software project, you build a feature; you roughly know when it will be finished. In a data project, you build a result that depends on a material you don't control: source data. Three differences structure this entire file.

  1. The material is unknown at the start. Until you've profiled the sources (NULL rate, duplicates, value domains, cross-system consistency), you don't know whether the request is feasible. Uncertainty is structural and concentrated at the beginning of the project.
  2. The output is a number, not a feature. A feature is correct or not against a specification. A number (“1,284 visits in week 38”) is correct if the business recognizes it — which assumes reconciliation with a reference that may itself be debatable. Acceptance testing is therefore a negotiation of definitions, not just verification.
  3. The product lives on after delivery. Sources drift, volumes grow, business definitions evolve. A “finished” delivery that is not operated and monitored degrades within a few months.
🧪 Example

A request for “number of visits per salesperson per week” sounds trivial. Profiling reveals that 6% of visits are entered twice (offline sync replayed), that “week” differs between the finance team (ISO) and field teams (local Monday-Sunday), and that transferred salespeople change reporting lines during the month. None of these three points was in the request; each changes the number. That's the real work.

🟡 Practical — the five families of data projects#

Family Core question Typical deliverable Relevant methods
Analytics / machine learning Which model, with what performance? Model + scoring CRISP-DM, ASUM-DM, TDSP, MLOps
BI / warehouse / datamart Which reliable number for which decision? Dimensional model + reports Kimball, Scrum/Kanban, DataOps
Migration / integration Did everything arrive intact? Moved data + evidence Predictive/hybrid, reconciliation
Governance Who decides, who is accountable for what? Roles, policies, catalog DAMA-DMBOK, change management
Quality Which defect should be fixed, sustainably? Rules, controls, remediation plan DMAIC-like, DataOps
💡 Expert tip

Before choosing a method, classify the project in this grid. Many method errors come from treating a migration project (fixed-date delivery, zero loss) like an analytics discovery project (exploration, iterations), or the reverse. See Choosing Your Method and Hybridizing.

🔴 Expert — the shifted “cone of uncertainty”#

Predictive methods assume uncertainty decreases with analysis. In data, a large share of uncertainty is only reduced through contact with real data, often after the official “analysis” phase. Consequences: (a) a profiling spike (1 to 5 days) must precede any date commitment; (b) estimation is done in ranges and revised after profiling; (c) sprint reviews on a data project must show reconciled numbers, not mockups. This point is developed in Scrum and data and measured by the 03 Data Project Management matrix.


2. CRISP-DM#

🟢 Novice — the model#

CRISP-DM (CRoss-Industry Standard Process for Data Mining) is a process model published as version 1.0 in 1999-2000 by an industry consortium (including SPSS, NCR, Daimler-Chrysler, OHRA). For years, it remained the most cited process model in data mining practitioner surveys; it has never had a single official successor.

It has six phases, iterative and not strictly sequential:

1. Business understanding2. Data understanding3. Data preparation4. Modeling5. Evaluation6. Deploymentobjectives not met
Feedback loops are the norm: preparation and modeling point back to data understanding; evaluation can point back to business need.Hover over or tap an element to read its details.
Phase Question Typical deliverables
Business understanding What objective, what success criterion? Business objectives, success criteria, project plan
Data understanding What data, what quality? Collection, description, exploration, and quality report
Data preparation How do we build the analysis table? Final dataset, cleaning and construction rules
Modeling Which technique, which parameters? Models, assumptions, technical evaluation
Evaluation Does the model meet the business objective? Process review, decision to proceed
Deployment How should it be used and monitored? Deployment plan, monitoring plan, final report

🟡 Practical — how to use it today#

CRISP-DM is a thinking framework, not a management framework: it doesn't say who, how much, or when. Its value is forcing you to start with the business and close the loop (the return arrows are the core of the model: you often go back from “data” to “business” because the objective was not realistic).

Effective use: make it the backbone of each cycle in an agile backlog — each analytics epic goes through the six phases, but in short slices. A sprint can cover “2→3” (profiling + preparation) on a limited scope.

✅ Good practice

Write the business success criterion before opening a single file (“reduce shelf stockouts by 10% across 50 pilot stores”), not just the technical criterion (“AUC > 0.8”). Evaluation in phase 5 must be able to say “technically good, useless for business.”

⚠️ Pitfall

Symptom: a high-performing model never used. Cause: phases 1 and 6 rushed; deployment (process integration, change management) wasn't in the plan. Remedy: include in phase 1 the person who will act on the result and plan the deployment budget.

🔴 Expert — limits and extensions#

  • No post-deployment lifecycle: monitoring, retraining, and drift are barely mentioned → hence MLOps (section 8).
  • No teamwork layer: no roles, no tooling, no version control system for data and models → hence TDSP and ASUM-DM.
  • Documentation-heavy in version 1.0: useful for audits, heavy for short iterations. Adapt it: produce only deliverables that support a decision.
  • Relevance beyond ML: phase 2-3 (understanding and preparation) is universal and appears in any BI or migration initiative; the rest is specific to predictive modeling.

Ratings (context: team of 4 to 8 people, analytics or ML project):

Criterion Rating Rationale
Predictability 2/5 Provides neither estimation nor milestones; phase 2 uncertainty remains open
Adaptation to change 4/5 Iterative by design, explicit feedback loops
Risk control 3/5 Forces validation of the business objective; no formal risk management
Lightweightness 4/5 Lean framework, adaptable
Fit for data projects 5/5 Designed for that (analytics); less so for pure BI
Ease of adoption 5/5 Six phases, intuitive vocabulary
Scalability 2/5 Designed for one team, not a portfolio
Visibility / governance 2/5 No governance bodies, no indicators
Deliverable quality 3/5 Depends on local discipline

3. ASUM-DM#

🟢 Novice — an IBM extension#

ASUM-DM (Analytics Solutions Unified Method for Data Mining/Predictive Analytics) is a method published by IBM (2015) that extends CRISP-DM. It keeps CRISP-DM's analytical phases and adds a project management and operations layer. It is less widespread than CRISP-DM and mostly associated with the IBM ecosystem; to be verified regarding its current maintenance status, since its public documentation has become hard to locate.

What it brings, in spirit:

  • additional phases upstream and downstream: design, implementation, operations (operations), beyond simple deployment;
  • a project dimension: governance, risk management, roles;
  • the idea that analytical phases (understand, prepare, model, evaluate) are carried out in an agile and iterative way, while the project layer remains managed in a more traditional way.

🟡 Practical — when to cite it#

In a response or scoping document for a large enterprise client, ASUM-DM is reassuring: it shows that the cycle does not stop at deployment. In practice, a team that combines CRISP-DM and an agile backlog with explicit operations phases gets the same result without formally adopting ASUM-DM.

🔴 Expert — critical reading#

The real value is conceptual: separating the analytical loop (short, iterative) from the project loop (long, milestone-driven). This is the same separation as in an “agile within predictive” hybrid (see Choosing Your Method and Hybridizing). If your context is not IBM, keep the separation, not the name.

Criterion Rating Justification
Predictability 3/5 Explicit project layer, milestones
Adaptation to change 4/5 Iterative analytics
Risk control 3/5 Risk management planned, limited tooling
Lightweightness 2/5 More deliverables than CRISP-DM
Fit for data projects 4/5 Analytics; little pure BI
Ease of adoption 2/5 Scarce documentation, closed ecosystem
Scaling 3/5 Governance included
Visibility / governance 3/5 Roles and milestones
Deliverable quality 3/5 Depends on discipline

4. TDSP (Team Data Science Process)#

🟢 Novice — Microsoft's method#

The Team Data Science Process is a methodology published by Microsoft for data science teams. It offers a life cycle similar to CRISP-DM, a standardized repository structure, roles, and integration with Azure tooling (Azure DevOps for task and code tracking). Its life cycle has five stages: business understanding, data acquisition and understanding, modeling, deployment, customer acceptance testing.

Its uniqueness is not the cycle, but team industrialization: a project template (folder structure, report templates), a backlog linked to the repository, naming conventions. The maintenance status of TDSP documentation is to be verified: the reference page exists on Microsoft Learn, but Microsoft's focus has shifted toward MLOps and Fabric/Azure Machine Learning approaches (status as of 2026-10, not re-verified in detail).

🟡 Practical — what you can reuse without adopting it#

  • A standard project tree: data/ (raw, cleaned), code/, models/, reports/, docs/. It avoids each project reinventing its organization.
  • A standardized data quality report at stage 2 (reproducible profiling, not copy-pasted screenshots).
  • A definition of “done” that includes customer acceptance testing: the model is delivered only when the customer has accepted it based on written criteria.
💡 Expert tip

Even for a BI project, the idea of a repository template is transferable: a 00_Profiling folder (rerunnable profiling queries), 10_Model, 20_Loading, 30_Tests, 40_Reports. See Source Control for Data: SQL and Power BI.

🔴 Expert — limits#

TDSP assumes a data science team with notebooks, experiments, and compute infrastructure: a framework heavier than necessary for a team of 2 BI developers. The acceptance cycle is valuable but does not address drift after delivery — MLOps must be added.

Criterion Rating Justification
Predictability 3/5 Milestones and roles, no estimation
Adaptation to change 4/5 Iterative
Risk control 3/5 Customer acceptance testing, little risk management
Lightweightness 3/5 Useful templates but fairly comprehensive framework
Fit for data projects 4/5 Data science
Ease of adoption 3/5 Good original documentation, Microsoft anchoring
Scaling 3/5 Standardization across projects
Visibility / governance 3/5 Backlog linked to code
Deliverable quality 4/5 Templates, reproducibility

5. The Kimball Lifecycle#

🟢 Novice — the data warehouse reference#

Ralph Kimball and his coauthors described in The Data Warehouse Lifecycle Toolkit (“the Kimball Toolkit,” 2nd ed. 2008) a dimensional data warehouse project lifecycle. It is the historical BI method: it is centered on the business, dimensional modeling (facts and dimensions), and incremental delivery by business process.

Project planningframing, business requirementsTechnologyarchitecture, productsDatadimensional modelingETL design and developmentBI applicationsspecification, developmentDeployment→ maintenance → growth(new cycle)
Three parallel tracks after framing, brought together at deployment; the cycle restarts with growth.Hover over or tap an element to read its details.

Three parallel paths (technology, data, BI applications) converge toward deployment; the whole effort is framed by planning and requirements gathering, and followed by a growth cycle.

🟡 Practical — ideas that still matter#

Kimball idea Content Why it matters
Bus matrix Business processes (rows) × conformed dimensions (columns) Plans batches, avoids silos: each batch reuses dimensions already delivered
Conformed dimensions The same dimension (customer, product, date) shared across facts Makes it possible to cross-check figures without manual reconciliation
Grain Level of detail of a fact table, fixed before anything else #1 source of errors: mixing two grains distorts totals
Incremental delivery One business process at a time, one batch in 2 to 3 months Fast value, gradual learning
Dimensional model (star) Facts surrounded by denormalized dimensions Readability and performance for analytics
🧪 Example

SFA common thread: batch 1 = “visits” (grain: one visit), date, sales rep, customer dimensions; batch 2 = “orders” (grain: one order line) reuses date, customer, adds product; batch 3 = “shelf surveys” reuses product, customer. The bus matrix shows that customer is the critical conformed dimension: it must be handled first and carefully.

⚠️ Pitfall

Symptom: two reports give different totals for “the same” metric. Cause: non-conformed dimensions (two customer reference systems) or mixed grain. Remedy: review the bus matrix, enforce a single dimension, document the grain at the top of each fact table.

🔴 Expert — Kimball vs. modern practices#

  • Agile and Kimball are compatible: a Kimball batch can be broken down into stories (one dimension, one fact, one report). The classic Agile risk is delivering only reports without the conformed dimension — model debt accumulates. Keep the bus matrix as your roadmap.
  • ELT / lakehouse: Kimball's technical argument (model optimized for a relational engine) is still valid for the presentation layer; dimensional modeling appears again in the Power BI semantic model. What changes: storage (parquet, Delta) and when transformation happens.
  • Data Vault and Inmon: competing or complementary approaches (Inmon: normalized warehouse first; Data Vault: modeling for auditability and source flexibility). A common pattern: Data Vault or normalized zone in integration, Kimball star in presentation.
  • Historization: slowly changing dimensions (SCD type 1, 2, etc.), to be decided by attribute with the business — not by default. See the data matrix modeling theme.
Criterion Rating Justification
Predictability 4/5 Bus matrix, bounded batches
Adaptation to change 3/5 Good incrementally; a grain change is costly
Risk control 4/5 Model and requirements validated before loading
Lightweightness 3/5 Comprehensive method, adaptable
Fit for data projects 5/5 BI / warehouse-specific
Ease of adoption 4/5 Clear vocabulary, abundant literature
Scalability 4/5 Conformed dimensions = enterprise consistency
Visibility / governance 4/5 Bus matrix readable by the business
Deliverable quality 5/5 Consistent, documented models

6. DataOps#

🟢 Novice — applying the DevOps mindset to data#

DataOps refers to a set of practices that apply Agile, DevOps, and statistical process control (Lean manufacturing) ideas to the data production chain. The goal is to shorten lead time between a data request and its reliable delivery, while reducing production errors. The term was popularized around 2014-2015; a DataOps Manifesto was later published, with 18 principles.

The manifesto (read it at dataopsmanifesto.org) states values and principles. The most structuring ones, rephrased in my words:

Theme Principle (rephrased)
Value Satisfy the customer by continuously delivering useful analytics, early and often
Value Measure how analytics perform: it's the outcome that matters, not the code
Quality Treat pipelines as code; automate tests; nothing is delivered without testing
Quality Detect production anomalies early: “stop the line” when data is bad
Flow Reduce cycle time: from idea to production, shorter is better
Collaboration Teams (business, data, ops) talk daily
Reproducibility Version everything: code, configuration, environments, and if possible test datasets
Simplicity Simplicity (the art of maximizing work not done) is essential
Environments Provide disposable, on-demand environments to experiment safely
Improvement Regularly reflect on how to do better; retrospective

The fact of versioning data or its samples and creating disposable environments distinguishes DataOps from classic DevOps: data, unlike code, has volume, sensitivity, and state.

🟡 Practical — two pipelines, two loops#

A productive mental model: a data chain contains two pipelines that intersect.

  • The value pipeline (production): sources → transformations → model → reports, run every day. It must be robust, monitored, replayable.
  • The innovation pipeline (development): idea → development → test → deployment. It must be short and automated.

The two control loops: production quality (data tests at each run, alerts) and development quality (automated tests on every change, continuous integration). Technical detail is in CI/CD for data: foundations, datamarts, pipelines, and reports.

✅ Good practice

Start with runtime data tests (today's volume, key uniqueness, referential integrity, freshness): it's the smallest DataOps step with immediate gains. It turns “the report has been wrong since Monday” into “the alert triggered at 6 AM.”

⚠️ Pitfall

Symptom: “DataOps” becomes a purchased tool, not a practice. Cause: confusion between platform and discipline. Remedy: measure outcomes (delivery lead time, data incident rate, detection time), not the number of automated pipelines.

🔴 Expert — measuring DataOps#

Relevant indicators (to adapt): production lead time for a change; deployment frequency; data incident rate per month; time to detect then to fix; share of time spent on unplanned work (rework, fixes). They extend DORA metrics (see CI/CD: Continuous Integration and Continuous Delivery) with data-specific measures, developed in data matrix theme 06.

💡 Expert tip

Statistical process control (SPC) applied to daily volume (mean ± 3 standard deviations over a rolling 30-day window) detects a good share of silent failures (partial load, broken filter) without writing a business rule. It is a behavior alert, complementary to integrity rules.

Criterion Rating Justification
Predictability 3/5 Steady flow improves lead time predictability
Adaptation to change 5/5 Designed to deliver quickly and often
Risk control 4/5 Automated tests, early detection
Lightweightness 3/5 Real initial tooling cost
Fit for data projects 5/5 Specific
Ease of adoption 2/5 Requires cross-functional skills and culture
Scalability 4/5 Pipeline standardization
Visibility / governance 4/5 Metrics, logs, alerts
Deliverable quality 5/5 Quality built into the flow

7. Data products and Data Mesh#

🟢 Novice — thinking in “product” terms#

A data product (data product) is a dataset — or a service that provides one — designed, maintained, and offered as a product to consumers: with an owner, documentation, a service level, and measured quality. The core idea is to move from “a project that delivers tables” to “a team responsible for a product over time.”

Data Mesh is a paradigm described by Zhamak Dehghani (2019-2020 articles, Data Mesh book in 2022) that proposes, in response to the limits of a central warehouse, four principles:

  1. Domain ownership: business teams that produce data are responsible for it;
  2. Data as a product: each domain publishes reliable, discoverable products;
  3. Self-service platform: a platform team provides shared tooling;
  4. Federated computational governance: global rules, applied automatically, decided collectively.

🟡 Practical — what this changes for project management#

Dimension Traditional project Data product
Horizon Ends at delivery Continuous lifecycle
Team Formed then disbanded Stable, owner
Funding Project budget Product funding (continuous line)
Quality Delivery acceptance testing Service levels (SLO) continuously monitored
Documentation Delivery package Catalog, data contract, versioning
Consumers One identified client Several, known or unknown

The data contract (schema, semantics, freshness, expected quality, evolution rules) is the object that formalizes the producer-consumer relationship. It is handled like an API interface: any contract break is an announced major version change.

🧪 Example

An SFA datamart exposes three fact tables and their dimensions. Treating it as a product means: naming an owner; publishing a “contract” page (grain, freshness: D+1 at 7 a.m., keys, dictionary, business rules); announcing schema changes two versions ahead; tracking the rate of broken reports after each delivery. No new tool is required to get started.

🔴 Expert — Data Mesh: when and when not#

Data Mesh solves an organizational scale problem (dozens of domains, one central bottleneck). It fails when the organization lacks data skills in domains, lacks a platform, or lacks appetite for federated governance. For a single BI team of a few people, adopting the “product” vocabulary (owner, contract, SLO) makes sense; adopting the Data Mesh architecture does not. The ratings below apply to a mid-sized organization (200 to 2,000 people).

⚠️ Pitfall

Symptom: each domain publishes “its own” customer with its own definition. Cause: decentralization without conformed dimensions or real federated governance. Remedy: a small number of reference products (customer, product, date, organization) handled centrally, with other domains built on top of them.

Criterion Rating Justification
Predictability 2/5 Depends on each domain's maturity
Adaptation to change 4/5 Domain autonomy
Risk control 2/5 Risk of inconsistency and fragmentation
Lightweightness 2/5 Platform and governance must be built
Fit for data projects 4/5 Targets large organizations
Ease of adoption 1/5 Heavy organizational transformation
Scalability 5/5 That is its reason for being
Visibility / governance 3/5 Federated governance still to be proven
Deliverable quality 3/5 Varies by domain

8. MLOps and AIOps in brief#

🟢 Novice — two acronyms, two meanings#

  • MLOps: practices to industrialize a machine learning model: version data, code, and model; automate training, validation, deployment; monitor performance and drift; retrain. It is “DevOps for models.”
  • AIOps: an ambiguous term. In its original meaning (Gartner), using AI/ML to operate IT (alert correlation, anomaly detection, incident automation). Do not confuse it with “operating AI systems” (which falls under MLOps, and for generative AI, labels such as LLMOps).

🟡 Practical — what changes in project management#

A model is never “finished”: its behavior depends on current data. Therefore:

  • an explicit run budget (monitoring, retraining) from the framing stage;
  • two-stage acceptance testing: offline performance, then production performance (“shadow” mode or pilot);
  • a model registry (version, training data, metrics, owner);
  • alert thresholds for drift (population, variable distribution, measured performance when real outcomes are known).

🔴 Expert — specific pitfalls#

⚠️ Pitfall

Symptom: demand forecasting model performance slowly degrades with no alert. Cause: real-world behavior changes (new product line, new competition); no production metric is tracked, and the “true” result arrives only with delay. Remedy: monitor input drift (available immediately) while waiting for error measurement, and plan periodic retraining.

For a BI developer, a reasonable entry point is modest: a score produced by a scheduled job, stored in a table, consumed in a report, with its version and training date exposed. That is already minimal MLOps. See also AI in Planning and Version Control Tools.

Criterion (MLOps) Rating Justification
Predictability 3/5 Depends on data stability
Adaptation to change 4/5 Retraining can be automated
Risk control 4/5 Drift monitoring, registry
Lightweightness 2/5 Dedicated infrastructure and skills
Fit for data projects 4/5 Targets production models
Ease of adoption 2/5 Rare skills, heterogeneous tooling
Scalability 4/5 Standardization of model pipelines
Visibility / governance 4/5 Version traceability
Deliverable quality 4/5 Reproducibility

9. DAMA-DMBOK#

🟢 Novice — the data management framework#

The DMBOK (Data Management Body of Knowledge), published by DAMA International, is the framework for the data management discipline. Its 2nd edition (DMBOK2, 2017) structures the field into eleven knowledge areas, often represented as a “wheel” with data governance at the center:

  1. Data governance
  2. Data architecture
  3. Data modeling and design
  4. Data storage and operations
  5. Data security
  6. Data integration and interoperability
  7. Document and content management
  8. Reference data and master data
  9. Data warehousing and business intelligence
  10. Metadata management
  11. Data quality

It is not a project method: it is a vocabulary and a map (who does what, which activities, which deliverables, which roles). It serves as an audit framework and common language, especially with leadership.

🟡 Practical — how to use it without getting lost in it#

  • Assess the organization across each area (maturity grid) to decide where to invest, not to cover everything.
  • Name roles (data owner, data lead, data steward, architect): the most concrete contribution.
  • Align vocabulary: “reference data,” “master data,” and “metadata” are not the same.
✅ Good practice

Choose two or three areas with high leverage (often quality, metadata, governance) and treat them as real projects with measurable outcomes. A complete wheel with no priorities produces one more framework and no change.

🔴 Expert — critical use#

DMBOK is descriptive, not prescriptive: it does not say in what order, or with what budget. It is useful for a data manager or architect, but not very operational for a development team. The file's maturity matrices (Maturity Matrix — Data Project Management (PD), BI) operationalize part of these areas as verifiable milestones. Details on Data Governance and Organization.

Criterion Rating Justification
Predictability 1/5 Not a planning method
Adaptation to change 3/5 Flexible framework, since descriptive
Risk control 3/5 Covers security, quality, governance
Lightweightness 2/5 Dense body of work
Fit for data projects 4/5 Covers the full data scope
Ease of adoption 3/5 Common language, but heavy to apply
Scalability 4/5 Designed for the enterprise
Visibility / governance 5/5 Its reason for being
Deliverable quality 3/5 Depends on implementation

10. Data governance managed as a project#

🟢 Novice — what it is, what it is not#

Data governance is the exercise of authority and control (planning, monitoring, enforcement) over the management of data assets. Put simply: who decides what, under which rules, and who is accountable. It is not a tool (the catalog is only a support) nor an additional committee.

🟡 Practical — start it as a value-driven project#

A governance program fails when it is “top-down, exhaustive, with no visible benefit.” It succeeds when it starts from a concrete pain point.

Step Content Verifiable output
1. Pain point “Two different revenue figures in steering committee” Measured use case
2. Minimal scope One domain, 10 to 20 critical terms Validated business glossary
3. Roles Owner and manager for each term Named list
4. Rules Single definition, calculation rule, source of record One sheet per indicator
5. Mechanism Where changes are decided Written decision workflow
6. Control Automated compliance test Compliance report
7. Extension Next domain Roadmap
🧪 Example

In an SFA datamart, the indicator “coverage rate” (visited customers / customers in the portfolio) has three competing definitions (the denominator differs: active customers, customers in the master file, customers with an order over 12 months). The governance project produces one definition selected by the sales manager, documented in the datamart metadata, and two explicitly named variants if needed. Duration: 3 one-hour workshops and two calendar weeks — what costs is deciding, not documenting.

🔴 Expert — why it fails, how we know#

  • No sponsor able to arbitrate between two departments: governance is nothing more than institutionalized arbitration.
  • Roles without time allocation: “data steward” added to a job description without backfill is a fictional role. Indicator: how many hours per week, explicitly scheduled?
  • Documentation without control: a glossary that nothing verifies becomes outdated in six months. Link each definition to an automated test or a dated review.
  • Compliance as an afterthought: GDPR, regulated sectors — legitimate requirement, but to be treated as a design constraint, not as an afterthought (see the theme Security, Privacy, Compliance).

Ratings for governance as an approach (context: organization of 500+ people, identified sponsor): predictability 2/5, adaptability 3/5, risk control 4/5, lightweightness 2/5, adoption 2/5, visibility 5/5, deliverable quality 4/5. The main determinant is whether a sponsor is present: without one, everything drops by one point.


11. The data migration project#

🟢 Novice — why it is a project in its own right#

Migrating means moving data from one system to another while preserving meaning. Two errors are common: believing it is simple “technical copy-paste” and underestimating it; underestimating data cleansing and business validation. The cutover date is often fixed (contract end, shutdown of the old system): the project is more predictive than exploratory.

🟡 Practical — phases and controls#

Phase Key activities Control / evidence
Inventory Objects, volumes, dependencies, owners Catalog of migratable objects
Profiling Source quality, orphans, duplicates, encodings Source quality report
Mapping Source → target, transformation rules Mapping table validated by the business
Design Strategy (big bang, phased, parallel), rollback plan Documented cutover plan
Implementation Repeatable migration scripts Versioned, idempotent scripts
Rehearsals At least 2-3 full dry-run migrations Measured duration, listed anomalies
Reconciliation Counts, checksums, samples, business indicators Signed reconciliation report
Cutover Freeze, final migration, checks, go/no-go decision Sign-off report
Post-migration Hypercare, fixes, old-system archiving Closure

Dry-run rehearsals are the #1 risk lever: they turn the unknown (“how long?”) into measured data and reveal edge cases (special characters, out-of-range dates, orphan keys).

✅ Good practice

Write the rollback plan before cutover and time it during a rehearsal. A rollback plan that is never executed is a hypothesis.

⚠️ Pitfall

Symptom: migration “succeeds” (zero technical errors) but users find discrepancies at D+15. Cause: technical validation only (row count); no comparison of business results. Remedy: compare, before and after, business indicators selected with users (revenue by customer and by month, number of visits per sales rep, etc.), not just counts.

🔴 Expert — reconciliation and idempotence#

Robust reconciliation combines three levels: counts (number of rows per table, per partition), aggregates (sums of numeric columns, date min/max), fingerprints (checksum of rows or of a subset). Comparable T-SQL checksum example across two databases:

SELECT COUNT(*)                         AS nb_lignes,
       SUM(CAST(montant AS decimal(19,4))) AS somme_montant,
       CHECKSUM_AGG(BINARY_CHECKSUM(*)) AS empreinte
FROM   dbo.Commande
WHERE  date_commande >= '2026-01-01';

(CHECKSUM_AGG/BINARY_CHECKSUM can have collisions: good for detecting a discrepancy, insufficient to prove equality; plan a targeted complementary check.)

The migration process must be idempotent: replaying it on the same input yields the same result with no duplicates. Technique: natural key + MERGE or INSERT … WHERE NOT EXISTS, processed-batch log. See CI/CD for data: foundations, datamarts, pipelines, and reports.

Criterion Rating Justification
Predictability 4/5 Bounded scope, measurable rehearsals
Adaptability to change 2/5 Fixed cutover date
Risk control 4/5 Rehearsals, reconciliation, rollback
Lightweightness 2/5 Required documentation and evidence
Ease of adoption 4/5 Intuitive approach
Scalability 3/5 Depends on the number of objects
Visibility / governance 4/5 Evidence and sign-off reports
Deliverable quality 4/5 If business reconciliation is done

12. The BI / datamart project#

🟢 Novice — the most common form#

A BI project builds a datamart (dimensional model for a business domain) and reports that consume it. It follows: needs → model → loading → reports → acceptance testing → operations. It is a project that is half software engineering, half data investigation.

🟡 Practical — a recommended composite method#

Layer Method Role
Scoping and modeling Kimball (bus matrix, grain, conformed dimensions) Structure value in batches
Management Scrum or Kanban (see Scrum and data) Pace, visibility, adaptation
Delivery Lightweight DataOps: versioning, testing, replayable kits Deployment reliability
Governance Glossary, owner per metric Stable definitions
Acceptance testing Reconciliation with a reference, signed business validation Trust in the numbers

Typical sequence for a batch (3 to 8 weeks):

  1. Need and metrics: list of decisions to inform, metrics, and their written definitions.
  2. Source profiling (spike): feasibility, quality, volume.
  3. Dimensional model: grain, facts, dimensions, historization decided with the business.
  4. Loading: replayable transformations, data tests.
  5. Semantic model and reports: measures, security (RLS), translations.
  6. Business acceptance testing: reconciliation with a reference.
  7. Delivery: versioned kit, release notes, light training.
  8. Operations: monitoring, support, feedback collection.
🧪 Example

SFA thread: “visits” batch. Need: track portfolio coverage. Profiling: 6% synchronization duplicates → deduplication rule decided. Model: grain = visit; date/sales rep/customer dimensions (SCD2 on sales rep assignment). Loading: idempotent upsert on visit identifier. Acceptance testing: reconciliation of number of visits per sales rep with the application extract: tolerated variance 0 for the week, 2 visits tolerated on older history (documented cause). Delivery: kit no. N+1 with notes. Total: 5 weeks, including 1 for profiling and 1 for acceptance testing.

⚠️ Pitfall

Symptom: the report is delivered, nobody opens it. Cause: designed to “show numbers” rather than support a decision; adoption not addressed. Remedy: start from a named decision and a named user; measure usage (opens, active users) from the first weeks. See Adoption and Change Management.

🔴 Expert — structuring trade-offs#

  • Where to put logic: transformation in SQL (reusable by all tools) rather than in the semantic model (locked into one tool). Measures, however, live in the model. Details: Semantic Model and Data Layer and ETL.
  • Deliver fast without model debt: a fast batch that bypasses a conformed dimension creates debt that will be paid in the next batch.
  • Versions: a report consumed by external clients or subsidiaries requires not breaking column and measure names — treat the model as an API (see Versioning and Industrialization of Reports).
  • Power BI reporting: target architectures are detailed in 04 Power BI Reporting.
Criterion (composite Kimball + agile + DataOps method) Rating Justification
Predictability 4/5 Bounded batches, steady flow
Adaptation to change 4/5 Iterative by batches
Risk control 4/5 Profiling, acceptance testing, tests
Lightweightness 3/5 Non-compressible modeling rigor
Ease of adoption 3/5 Requires cross-functional skills
Scalability 4/5 Conformed dimensions
Visibility / governance 4/5 Backlog + bus matrix
Deliverable quality 5/5 Model, tests, business acceptance testing

13. Data quality projects#

🟢 Novice — fix the cause, not just the symptom#

A data quality project aims to measure and then improve data reliability. The common mistake: clean once (a “major cleanup”) and then find that defects come back. Quality is a process — trace back to the cause (entry, interface, business rule, integration) and put in a lasting control.

🟡 Practical — the quality loop#

A loop inspired by DMAIC (Define, Measure, Analyze, Improve, Control):

Step Data application Example
Define Choose a defect with high business impact Duplicate customers in the database
Measure Define quality dimensions and measure them Duplicate rate: 4.1%
Analyze Find the root cause Offline field entry without existence check
Improve Fix at the source + remediate existing stock Entry validation + stock merge
Control Recurring automated measurement + alert Daily test, 0.5% threshold

Common dimensions (vocabulary from data quality literature, to be defined locally): accuracy, completeness, consistency, uniqueness, freshness/currency, validity (format/domain compliance), referential integrity.

✅ Good practice

Associate each quality rule with: an owner, a severity (blocking or warning), an action (who fixes it, where). A rule without an owner generates ignored alerts.

⚠️ Pitfall

Symptom: fixing data in the datamart every month. Cause: downstream correction of a defect that originates upstream. Remedy: make the cost visible (hours of correction per month) to negotiate correction at the source, and only correct downstream if the source is out of reach — then document the correction rule as a business rule.

🔴 Expert — trade-offs#

  • Block or let through: should poor-quality data prevent loading? Practical rule: block for defects that make aggregates wrong (null key, duplicate fact); let through with a signal for descriptive defects (missing label), with an “unknown” member in the dimension.
  • Quarantine: write rejected rows to an exception table usable by the business, not to a technical log.
  • Cost measurement: value calculation is approximate (correction time, delayed decisions); an honest, ordered estimate is better than an invented precise number.
  • Link to the matrix: Data Quality topic for maturity levels.
Criterion Rating Justification
Predictability 3/5 Easy measurement, random cause correction
Adaptation to change 3/5 Iterative loop
Risk control 4/5 Reduces business and compliance risks
Lightweightness 3/5 Depends on number of rules
Ease of adoption 3/5 Culture and ownership to build
Scalability 3/5 Rule catalog to maintain
Visibility / governance 4/5 Quality dashboards
Deliverable quality 4/5 If root cause addressed

14. Comparison Table and Ratings#

Summary (expert, contextual assessments: team of 3 to 10 people, data project of 3 to 12 months; see RATING). The approaches are not all of the same nature — some are processes, others are frameworks or philosophies — so the comparison is indicative. Full comparison with general methods: 08 Comparison of Methods.

Method Nature Predict. Adapt. Risk Lightweight Data fit Adoption Scale Gov. Deliverables
CRISP-DM Analytical process 2 4 3 4 5 5 2 2 3
ASUM-DM Process + project 3 4 3 2 4 2 3 3 3
TDSP Process + tooling 3 4 3 3 4 3 3 3 4
Kimball BI/warehouse cycle 4 3 4 3 5 4 4 4 5
DataOps Philosophy + practices 3 5 4 3 5 2 4 4 5
Data Mesh Organizational paradigm 2 4 2 2 4 1 5 3 3
MLOps Operational practices 3 4 4 2 4 2 4 4 4
DAMA-DMBOK Framework 1 3 3 2 4 3 4 5 3

(Ratings out of 5, the “Predict.” column = predictability, etc.)

How to read it:

  • Kimball and DataOps are the two pillars of a BI project, and they complement each other (model + flow); you get the best of Kimball + Scrum/Kanban + DataOps.
  • CRISP-DM is the best entry point for an analytics project; MLOps takes over after deployment.
  • DAMA-DMBOK and Data Mesh are organizational in nature; they do not replace a project method.
  • No single method covers modeling, flow, governance, and business acceptance testing all at once: the art is to assemble (Choosing Your Method and Hybridizing).

Quick decision tree:

Does the project producea predictive model?CRISP-DM (or TDSP) for the cycle+ MLOps after deploymentAre we building a warehouse,a datamart, or reports?Kimball (batches) + Scrum / Kanban+ lightweight DataOpsAre we moving datafrom one system to another?Migration planrehearsals, reconciliation, rollbackIs this a workstream on rules,roles, and definitions?Governance as a projectpain point → roles → rules → controlRecurring defect?quality loop (DMAIC-like)yesnoyesnoyesnoyesno
Hover over or tap an element to read its details.

15. Pitfalls and good practices#

The 40+ cross-functional pitfalls and 30+ good practices are grouped in 13 Pitfalls and good practices in project management (cross-functional summary). Those specific to this file:

Pitfall Symptom Cause Remedy
“All-in-one” method Looking for THE data method Methods cover different angles Assemble: model, manage, industrialize
Estimating before profiling Promised date is impossible Data uncertainty Profiling spike, ranges
Model without deployment Brilliant POC, never used “Deployment” phase ignored Operational sponsor, run budget
Decorative governance Glossary never consulted No decision-maker, no control One pain point, one sponsor, one test
“Technical” migration Business gaps at D+15 Technical-only checks Reconciliation by business indicators
Premature Data Mesh Each domain redefines “customer” Decentralization without platform Centralized reference products
Downstream quality Monthly manual fixes Upstream cause not addressed Fix at the source, make cost visible
🤖 AI

AI helps draft a profiling plan, generate control queries, and propose a first glossary from column names, but it replaces neither definition decisions (which are business decisions) nor validation of a figure.


16. AI Contribution#

Use case Gain Risk Maturity Prerequisites Safeguards
Generate profiling queries (NULLs, duplicates, domains) 4/5 2/5 4/5 Accessible schema, read permissions Human review, run on a copy
Propose a glossary from column names and examples 3/5 3/5 3/5 Minimal data dictionary Validation by the business owner
Draft quality rules (SQL) from a description 4/5 3/5 3/5 Written definition of the rule Test on known dataset, review
Match labels (fuzzy deduplication) 3/5 4/5 3/5 Labeled sample set Threshold, manual review of edge cases
Generate model documentation (column descriptions) 4/5 2/5 4/5 Readable model and metadata Review, source marked “generated”
Choose the project method 2/5 3/5 2/5 Detailed context Does not replace a scoping workshop

Sample prompt (to run on an anonymized sample):

Here is the schema of a SQL Server table (columns, types, 20 anonymized sample rows).
1) Propose 10 quality checks in T-SQL (uniqueness, completeness, validity, date consistency).
2) For each, indicate severity (blocking/warning) and the question to ask the business.
3) Do not invent any business rule: flag what is an assumption.
⚠️ Pitfall

Never paste real personal data into an unapproved assistant: anonymize or pseudonymize first, and check the tool policy. Details: AI for Project Management (General Then Data).

What AI does not replace: definition arbitration between two departments, accountability for a published figure, context knowledge (why this strange rule exists).


17. See also#